Client:
|
Topharm Pharmaceutical Expansion
|
| Project Manager: |
Vanbots Construction Corporation
|
Architect:
|
Whitney Bailey Associates Inc.
|
| Engineer: |
Amec
|
| Total Construction Cost: |
$147 million
|
| |
|
Apotex group of companies that required a manufacturing facility to be constructed and commissioned in less than 1 year.
Mobilized on site with custom CAD trailer to produce Interference and spool drawings directly to field.
Building structure was well in advance before tendering of mechanical contractor required Kelson’s management team to mobilize in short order and provide key layouts to suit mechanical systems.
With Kelson's CAD team on site working with Apotex design consultants this $30 million mechanical project was completed on time and on budget.